Matheson appointed the Lafferty Team to project manage their new office based in Penrose Dock, Cork City.

Matheson is initially occupying the space with plans of expansion to the floorplate in the future. This element had to be considered within the works. The building was designed to target minimum Gold LEED standard. A key challenge with this project was that prior to commencing on site, the client requested a complete redesign of the project in line with the evolving workplace. Lafferty were tasked with coordinating this major change including additional scope in line with the existing construction budget. Several value engineering workshops were held and effective budget management by Lafferty helped the client achieve their objectives.